Challenges:

  • PASSMN January Meeting – details are getting ironed out
  • Learning the stuff needed for the PASSMN Website
  • Deploy DB analysis – verify incremental deploys match full deploys for Project A2 (smaller project – from here on known as A2)
  • Performance Analysis – a few procedures had to be analyzed for performance improvements from A2
  • A couple of VT (Verification Testing) procedures needed to be altered
  • Coding on Project B – altering procedures for schema changes
  • Wrote Powershell script to deploy all DB changes locally

Good Reading from the Week:

The Week Ahead:

  • Project B is still behind.
  • Project A2 still needs some of my time
  • On Call for Production

 